Tri Harder Part 5 – What happens if the carbon intensity of the grid improves?

As more and more people becoming aware and believe in global warming the greater emphasis will be placed on action to decarbonise our grid. But what does that mean to trigeneration systems if the carbon intensity of the grid improves?

In Part 1 of Tri Harder I talked about the different carbon intensities of grid electricity around the world. Australia has one of the worst performing power grids in terms of carbon. In Part 2 of Tri Harder I talked about the difference in the carbon intensity of the electricity grid around Australia. In Part 3 of Tri Harder I talked about the ongoing operational carbon savings of trigeneration in each state. In Part 4 of Tri Harder I talked about

The next question – what happens to the carbon payback or carbon benefit of a trigeneration system if the grid decarbonises?

Decarbonising the grid will ultimately be driven by the government – not much hope there then! Or the government will be pressured by the voters (us) to decarbonise the grid – a bit more hope there. So what is there that we can use to help us understand how the grid would be decarbonised in response to pressure from us? At the moment the most relevant to Australia is the work done Professor Ross Garnaut undertook a Climate Change Review in 2007.

Within the review Garnaut outlined to options for Australia the first was to achieve a maximum of 450ppm, this was called Garnaut-25 as it committed to a 25% reduction in CO2 levels by 2020. He also outlined a fall back position of limiting to 550ppm by committing to a 10% reduction by 2020 – this was called Garnaut-10. Bear in mind that the current thinking to limit global average temperatures to less than a 2degree rise is 350ppm, not 450 or 550ppm but 350ppm.

Translating Garnaut 10 and 25 to the Australian electricity grid looks like this.

grid garnauts copy

There is predicted to be some improvement in the current grid even if Garnaut is ignored – new efficiencies, technologies etc. However, what should be noted is that the black line Garnaut-25 is to limit us to 450ppm, 350ppm limit would be much lower than this!

So what does this mean to our trigeneration systems?

Let’s take the same building, trigen size and set of assumptions that we have used in the previous posts.

NSW - full operation copy

NSW – Operation starts in 2013

Well, if trigen is compared to current grid then a carbon payback of about 4 years against grid, 4 years against Garnaut-10 and 5 years against Garnaut-25 should be achieved. On an year by year basis ignoring the embodied carbon the grid carbon intensity would be better than trigen in 2018 under Garnaut-25 and 2030 under Garnaut-10.

Now, how about if we are considering trigeneration for a building but we havent designed or built it yet. Well, if we assume that first year of operation is 2016 the graph looks like this.

NSW - 2016 opertion copy

NSW – Operation starts in 2016

The first thing to note is that the trigen option is still achieving a carbon payback in about 5 years against Garnaut-25 and 4 years against Garnaut-10 and current grid. But it should be noted that Garnaut-25 becomes better than trigeneration at the end of the life of the first engine – basically its ok for 12 years but you wouldn’t continue with a new engine after that.

Now, the most important thing with trigeneration is that it is run for as long and as often as possible. To highlight this, the graph below considers a poorly designed trigeneration where the base load of the building consistently drops below the engine size and the trigeneration system only ends up operating for 50% of its designed run hours.

NSW - 2016 opertion 50p copy

NSW – Operation starts 2016, 50% of designed run hours

As can be seen the run hours has a significant impact. The trigeneration system carbon never pays back against Garnaut-25, pays back after 8 years against Garnaut-10 with the first engine but wouldn’t stack up with a refurbishment of the second engine.

So, as can be seen in the above graphs in NSW decarbonising of the grid will start to have an impact on the carbon payback of trigeneration, even more of an impact the later the first year of operation is. For example, if the building is being designed now (2013) and it achieves practical completion in 2016 then if the building doesn’t achieve for say 2 years then the trigeneration might not be operational until 2018. If this is the case trigeneration does not acheive a carbon payback against Garnaut-25 even at full run hours.

The analysis also clearly demonstrates the importance of run hours of the trigeneration system, if the run hours are not maximised it will have significant impact on carbon payback as well as financial payback. If the trigeneration system is only run for half the hours it would be designed for in an office building it doubles the carbon and financial payback.

Calculating the exact benefit and cost of a trigeneration system should be done for each individual building as the profile of electrical demand, cooling demand and operational profile will vary the calculations. If you are looking at a trigeneration system and need help please email me at s.wild@cundall.com.au

The next Tri Harder posts will go into more detail on:

Tri Harder Part 6 – What about flue emissions and maintenance?

Tri Harder The Final Chapter – Why do we have so many trigeneration systems going into office buildings and how do I know if trigeneration is right for my building?

2 Comments on “Tri Harder Part 5 – What happens if the carbon intensity of the grid improves?

  1. Pingback: Tri Harder Part 6 – What about flue emissions and maintenance? – Simon Wild

  2. Pingback: Disruptive Tech Property Impact – Renewable Electricity « SIMON WILD

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: